6725 Thrasher Road, Holly Springs, NC — Daventry (25-REZ-05): 240 Lots, Approved Unanimously

A permit & zoning feasibility pre-screen compiled entirely from public records — an approved conditional rezoning documented end-to-end: what was approved, on what recorded conditions, and what remains open after the vote, on a site whose case-packet acreage does not reconcile with the county cadastre. Prepared 2026-11-28 · Wake County.

Case
25-REZ-05 — approved 2026-10-20
Area
127.09 acres (case packet)
County
Wake
Zoning
RR → SR-CD (RZ26-07)
Programme
240 single-family lots
Flood
Zone X (no SFHA)

Key findings

Permit & Zoning Feasibility Pre-Screen Dossier — SAMPLE 4

Prepared: 2026-11-28 Product: Pre-acquisition permit and zoning feasibility pre-screen, Raleigh–Durham–Chapel Hill (Triangle), North Carolina Basis: Public records and published regulations only. No valuation, no appraisal, no legal conclusion is offered in this dossier (see §8, Scope & Disclaimer).

This dossier compiles public records and published regulations; it is not a legal opinion. Retain NC land-use counsel to confirm.


1. Cover / Subject Identification

Item Finding Source
Subject address 6725 Thrasher Road, Holly Springs, NC 27540 (principal parcel; the rezoning site also takes in three associated parcels listed below) Town of Holly Springs, Town Council meeting record, October 20, 2026; Wake County Parcels record for PIN 0647-31-3352 (site address)
Case Rezoning 25-REZ-05 — Daventry, approved by Ordinance RZ26-07 (see §4) Town Council meeting record, October 20, 2026
Parcel 1 (principal) PIN 0647-31-3352 (PIN_NUM 0647313352); REID 0075086; site address 6725 Thrasher Rd; county land class "Mobile Home Park"; parcel description "BUCKHORN LD" Wake County Property / Parcels FeatureServer (maps.wakegov.com), direct PIN query, accessed 2026-11-28
Parcel 2 PIN 0647-40-1596 (PIN_NUM 0647401596); REID 0367153; site address 0 Thrasher Rd; land class "Acre With Improvement, No House"; description "TR1 PROP OF WADE & JOYCE TEMPLE BM2007-02181" Wake County Parcels FeatureServer, accessed 2026-11-28
Parcel 3 PIN 0646-39-9748 (PIN_NUM 0646399748); REID 0367152; site address 0 Thrasher Rd; land class "Vacant"; description "TR2 PROP OF WADE & JOYCE TEMPLE BM2007-02181" Wake County Parcels FeatureServer, accessed 2026-11-28
Parcel 4 PIN 0646-49-1644 (PIN_NUM 0646491644); REID 0296060; site address 0 Adcock Rd; 0.03 acre; listed in the Town's agenda item for this case Wake County Parcels FeatureServer, accessed 2026-11-28; Town Council agenda item 20, October 20, 2026
Owners of record (county record, current) Parcels 1–2: Temple Manor LLC (Deed Book 020299, Page 01925, recorded July 31, 2026 — county DEED_DATE field converted from epoch). Parcel 3: Templar Investments LLC (Deed Book 012914, Page 01639, recorded January 16, 2008). Parcel 4: Temple, Wade P Temple, Joyce A Wake County Parcels FeatureServer, accessed 2026-11-28
Owner listing in the case packet The Town's agenda materials list the owners as "Temple, Wade P Temple, Joyce A" — a listing that appears to predate the July 31, 2026 deed to Temple Manor LLC recorded in the county record above Town Council agenda item 20, October 20, 2026; Wake County Parcels FeatureServer
Applicant Stanley Martin Homes (not the owner of record). Agent: Laura Holloman, McAdams. Applicant's attorney in the hearings: Jason Barron. A summary from the property owners filed with the application states that no sale had taken place as of the application Town of Holly Springs Planning Board minutes summary, August 25, 2026; Town Council minutes, July 21, 2026 (CivicClerk); Holly Springs Daily, October 2026 (reporting the owners' summary filed with the application)
Current use Country Creek mobile home park — 65 mobile homes; residents own their homes and lease the lots (owners' summary filed with the application); gravel roadways; the park is served by well and septic; originally developed under Wake County standards and brought into the Town's extraterritorial jurisdiction in 2017 Town Council meeting record / staff presentation transcript, October 20, 2026; Holly Springs Daily, October 2026
Jurisdiction Town of Holly Springs extraterritorial jurisdiction (ETJ), Wake County, NC — the county record shows no municipal city code for the parcels and planning jurisdiction "HS"; the Town's record states the land is outside the town limits, where the Town controls zoning Wake County Parcels FeatureServer (CITY_DECODE / PLANNING_JURISDICTION fields), accessed 2026-11-28; Holly Springs Daily, October 2026
Area — case packet figure 127.09 acres (the figure used throughout the Town's case materials; the approved density of ≈1.89 units/acre is computed on it — see the reconciliation note below) Town of Holly Springs, rezoning case 25-REZ-05 packet and meeting records, 2026
Area — county records (reconciliation) County deeded acreage for the four parcels totals 159.52 acres (110.97 + 30.52 + 18.0 + 0.03); county GIS-computed area totals 143.24 acres (94.71 + 30.58 + 17.92 + 0.03). On the principal parcel alone, deeded acreage (110.97) and GIS area (94.71) differ by about 15%. Neither county total reconciles with the packet's 127.09 acres, and the difference exceeds 1% on every basis. The packet figure is used in this dossier only where the case record itself uses it (density, tree-preservation ratio); a boundary survey is a necessary pre-purchase item, and no area figure in this dossier should be relied on for a transaction Wake County Parcels FeatureServer (DEED_ACRES / CALC_AREA fields), accessed 2026-11-28; arithmetic by this dossier
County tax / assessed records for the site parcels Confirmed from Wake County's own Parcels service, 2026-11-28. Parcel 1: total assessed $11,320,263 (land $11,283,163; building $37,100). Parcel 2: $1,321,530 (land $1,200,140; building $121,390). Parcel 3: $761,053 (land $761,053; building $0). Parcel 4: $1,950. These are tax-administration records, not valuations or appraisals; no valuation opinion is expressed in any event (see §8) Wake County Parcels FeatureServer (TOTAL_VALUE_ASSD / LAND_VAL / BLDG_VAL fields), direct PIN queries, accessed 2026-11-28

Why this parcel was selected for the sample. It is the mirror image of Sample 1: the same town, the same RR starting district, a case heard in the same season — with the opposite outcome. Where Sample 1's 53-lot case (25-REZ-08) was deferred after a deadlocked Planning Board, this 240-lot case was approved unanimously, together with its utility allocation and a development agreement. Documenting an approved case tests the other half of the product: not "what is pending and why," but "what exactly was approved, on what recorded conditions, and what remains open after the vote" — including two features Sample 1 did not present, an occupied site (65 households) with relocation terms written into a development agreement, and a case-packet acreage that does not reconcile with the county cadastre.


2. Zoning — Before and After the Case

2.1 District before the case: RR — Rural Residential

2.2 RR development standards (UDO Table 2.2.1-A, §2.2.1)

Standard RR requirement
Maximum gross density 0.5 units/acre (1.0 units/acre only with a Conditional Zoning District)
Minimum lot area — detached dwelling, standard subdivision 2 acres
Minimum lot area — detached dwelling with Conditional Zoning District 1 acre
Minimum lot width at setback line — detached dwelling 100 ft
Minimum lot frontage 50 ft
Thoroughfare setback 50 ft
Front setback (minimum) 20 ft
Side setback — interior (minimum) 10 ft
Side setback — corner (minimum) 20 ft
Rear setback (minimum) 25 ft
Maximum primary building height 35 ft (50 ft with a Conditional Zoning District)

Source: Town of Holly Springs UDO, Table 2.2.1-A (Supplement #7), accessed 2026-11-27.

Arithmetic consequence (facts only, no opinion): at the by-right RR density of 0.5 units/acre applied to the packet's 127.09 acres, the gross ceiling is approximately 63 detached lots before open-space, street and utility deductions; at the 2-acre minimum lot size the same order of ceiling results. The existing mobile home park is a pre-existing use developed under Wake County standards (see §1); its status under the prior district is a matter of record, and any question about the treatment of a specific existing or proposed use is a determination for the Town and the client's counsel.

2.3 District after the case: SR-CD (Ordinance RZ26-07)

2.4 The approved programme and the conditions visible in the public record


3. Entitlement Pathway & Timeline

3.1 Posture after an approved conditional rezoning

With the rezoning adopted, the recorded next steps for this project are a quasi-judicial major subdivision proceeding, followed by civil construction drawings (administrative), per Town staff's description of the sequence at the July 21, 2026 hearing and the October 20, 2026 hearing. A utility allocation — a separate Council decision under the Town's Water Resource Management Policy — was approved together with this rezoning (see §6.2). Whether any particular later filing is complete or timely is a matter for the Town's records at the time of inquiry. Sources: Town Council minutes, July 21, 2026; Town Council meeting record, October 20, 2026.

3.2 Statutory steps for a rezoning (N.C.G.S. Chapter 160D, Article 6)

Step Requirement Citation
1. Pre-submittal Sketch Plan Review (pre-submittal) meeting must be held at least 5 business days before, and no more than 8 weeks before, the petition submittal deadline; a Traffic Impact Analysis scope determination is required from Development Services before that meeting Town of Holly Springs, Development Procedures Manual, Appendix A.02 (Comprehensive Plan Amendment / Rezoning packet), accessed 2026-11-27
2. Neighbourhood meeting Required under the UDO / DPM packet process; the applicant must document notice (letter and recipient list) and file a signed neighbourhood meeting report UDO §§11.5, 13 (neighbourhood meeting provisions, as amended by Ordinances 22-29, 25-32, 26-07)
3. Filing Complete petition filed as a single PDF via the Town's CityView portal, with petition form, vicinity map, plan consistency statement and fees DPM Appendix A.02
4. Planning Board review All proposed zoning-map amendments shall be submitted to the planning board for review and comment; if no written report is received within 30 days of referral, the governing board may act without it. The planning board must advise on plan consistency; its recommendation does not bind the governing board N.C.G.S. §160D-604(b), (d)
5. Legislative hearing — published notice The governing board shall hold a legislative hearing before adopting any amendment. Notice must be published once a week for two successive calendar weeks, first publication not less than 10 nor more than 25 days before the hearing N.C.G.S. §160D-601(a)
6. Legislative hearing — mailed & posted notice Owners of the affected parcel and of all abutting parcels must be mailed notice by first-class mail, deposited at least 10 but not more than 25 days before the hearing; notice must also be prominently posted on the site or adjacent right-of-way within the same window N.C.G.S. §160D-602(a), (c)
7. Governing board decision Adoption is by ordinance. The board must approve (i) a plan consistency statement and (ii) for a map amendment, a statement of reasonableness (they may be a single statement) N.C.G.S. §§160D-601(c), 160D-605(a)–(c)
8. After rezoning Separate major subdivision / development plan approval, utility allocation, then construction drawings (UDO §§11.10, 11.11, 11.14; Water Resource Management Policy, §6.2 below) N.C.G.S. §160D-601(e); UDO Ch. 11

3.3 Observed timeline for case 25-REZ-05 on this site (public record)


4. Permit & Case History

4.1 Subject site

Date Event Source
(park's origin) Country Creek mobile home park developed under Wake County standards Town Council staff presentation, October 20, 2026 (transcript)
2017 Site brought into the Town of Holly Springs extraterritorial jurisdiction Town Council staff presentation, October 20, 2026 (transcript)
January 16, 2008 Deed for Parcel 3 (Templar Investments LLC), Book 012914, Page 01639 Wake County Parcels record, accessed 2026-11-28
April 2025 First neighbourhood meeting for the rezoning proposal Town Council minutes, July 21, 2026 (CivicClerk)
(during the process) A neighbourhood meeting held for park residents drew no attendees, as reported to the Planning Board Planning Board minutes summary, August 25, 2026
July 21, 2026 Town Council public hearing; proposal at 255 single-family units, 2.06 units/acre; staff outline the project's history and commitments (see §2.4) Town Council minutes, July 21, 2026 (CivicClerk)
July 31, 2026 Deed recorded for Parcels 1–2 to Temple Manor LLC, Book 020299, Page 01925 (county DEED_DATE field; recorded during the case's pendency, after the public hearing) Wake County Parcels record, accessed 2026-11-28
August 25, 2026 Planning Board: plan consistency statement 5–1; recommendation to approve 5–1; recorded objections — no connection to Duncan Cook Road, and the proposed 5-foot side setback (see §2.4) Planning Board minutes summary, August 25, 2026
October 20, 2026 Town Council approved unanimously (6–0): Ordinance RZ26-07 (RR → SR-CD, 240 lots); the utility allocation; and the development agreement subject to the changes in §2.4. The minutes of this meeting were approved on November 17, 2026 (Town Council consent agenda; correction logged 2026-11-29 after re-verification against the official agenda and decision lists) Town Council meeting record and minutes summary, October 20, 2026
After October 20, 2026 No major subdivision filing, construction start, or further case action for this site was found in free public sources as of 2026-11-28. Multiple reports of the approval note expressly that a rezoning is not a building or grading permit and that no construction start has been announced Web search of Town meeting records and case coverage, 2026-11-28
Building / site permits on the parcels themselves Not found in free public sources as of 2026-11-28. No building permit record for the PINs was retrievable from the Town's CityView portal or Wake County records without an account / interactive session. Attempted: Town of Holly Springs CityView portal (registration-gated), Wake County Real Estate Data, web search by address and PIN Attempted 2026-11-28

4.2 Immediately surrounding activity documented in the same public record


5. Comparable Cases Nearby (Holly Springs, same RR starting point)

Case Location Change Scale Outcome & date Source
25-REZ-08 — 2420 Avent Ferry Road (Sample 1 of this series) 2420 Avent Ferry Road RR → SR-CD (≈90%) + NMX-CD (≈10%) requested 32.286 acres; 30–53 detached dwellings and 5,000–16,000 sq ft commercial Pending. Planning Board deadlocked 3–3 on a motion to recommend denial (July 28, 2026); Town Council deferred unanimously on August 18, 2026 for clarified conditions; no final decision recorded in free public sources as of 2026-11-28 Town Planning Board minutes summary, July 28, 2026; Town Council meeting record, August 18, 2026
25-REZ-02 — Powell Place 7051 & 7121 Rouse Road RR → NR-CD requested 32.7 acres; 97 units (55 detached, 42 attached) Planning Board recommended approval 6–1; the Council approval motion failed 2–3 on May 19, 2026 and the case was deferred; after a Rouse Road shoulder widening was added and the development-agreement text adjusted, the Council approved 3–1 on July 21, 2026 (rezoning, utility allocation and development agreement) Town of Holly Springs agenda items; P&Z Radar case file 25-REZ-02
25-REZ-07 — Grigsby Ave. Residential (Ordinance RZ25-09) Grigsby Avenue (5.82 acres, Wake PIN 0658086641) NR → NR-CD, with Future Land Use Map amendment 21 units (12 detached, 9 attached) Approved by Town Council, December 16, 2025, by 4–1, together with utility allocation and development agreement. Planning Board had recommended approval 7–0 Town of Holly Springs 2025 meeting record, accessed 2026-11-27
25-REZ-03 — 4016 Berman Edge Road (Ordinance RZ25-05) 4016 Berman Edge Road RR → SR (general use) 0.60 acre; minor subdivision into two lots of over 0.5 acre each Approved unanimously by Town Council, July 15, 2025. Planning Board had recommended approval 8–0 Town Council meeting record, July 15, 2025
26-DP-01 — Chandler Crossing (Resolution 26-25) — development plan, land rezoned June 2025 4500 Old Holly Springs Apex Road Development plan approval following a June 2025 rezoning and development agreement 17.36 acres; 298 apartments in three buildings Approved unanimously, October 20, 2026 (quasi-judicial hearing); Planning Board 9–0 Town Council meeting record, October 20, 2026

Pattern visible in the public record (facts only): in the same town and season, a 240-lot RR → SR-CD case with no commercial component was approved unanimously after two revision rounds, while a 53-lot case with a commercial pod was deferred after a deadlocked Planning Board, and a 97-unit RR → NR-CD case failed its first Council vote before approval in amended form. The recorded points of friction differ by case: here, displacement of an existing mobile home park and the housing-affordability plan conflict — addressed on the record through the development agreement's relocation terms (§2.4, §6.7); in the deferred case, the commercial component, access design and plan consistency of the mixed-use portion.


6. Constraints

6.1 Floodplain / FEMA

6.2 Water & sewer

6.3 Density, setback & design ceilings

See §§2.2–2.4. The figures that frame the site are: under the prior RR district, 0.5 units/acre and 2-acre minimum lots (gross ceiling ≈63 lots on the packet acreage, arithmetic in §2.2); under the adopted SR-CD, the approved master plan's 240 lots at 1.89 units/acre on the packet acreage, governed by the conditions of Ordinance RZ26-07 — whose full text was not obtained (§2.4). The one dimensional standard publicly contested in the record is the side setback (5 ft proposed vs. the 10-ft standard); the adopted figure is unverified. Lot dimensions in the approved master plan were not obtained in text form.

6.4 Open space, tree preservation & environmental

6.5 Transportation

The recorded transportation commitments for this case are the off-site turn lanes on the Piney Grove–Wilbon Road corridor, a new signal at Piney Grove–Wilbon and Adcock roads, and a payment toward a signal at Ralph Road (§2.4); the $100,000 fee-in-lieu originally associated with a Rouse Road signal was redirected at the decision hearing to relocation assistance, and is therefore recorded in §6.7 rather than here. The project's traffic impact analysis and trip counts were not obtained in text form. The Planning Board's recorded objection that the plan lacks a street connection to Duncan Cook Road stands in the record unaddressed by any later document found. Sources: Holly Springs Daily, October 2026; North Carolina Record meeting summary, October 20, 2026; Planning Board minutes summary, August 25, 2026.

6.6 Schools

Not found in free public sources as of 2026-11-28. No representation by Wake County Public Schools about school capacity for this case was found in the meeting records and coverage consulted (contrast Sample 1, where such a representation was recorded). Attempted: Town Council and Planning Board meeting records for 25-REZ-05, case coverage, 2026-11-28.

6.7 Existing occupancy & relocation terms (development agreement)


7. Sources

All sources are free public sources. No paywalled, account-gated or purchased source was used; items that could only be obtained that way are marked "Not found" in the body.

  1. Wake County — Property / Parcels FeatureServer (maps.wakegov.com): direct PIN queries for PIN_NUM 0647313352, 0647401596, 0646399748, 0646491644 (owner, deed book/page/date, deeded and GIS acreage, assessed land/building/total values, land class, planning jurisdiction), accessed 2026-11-28.
  2. FEMA — National Flood Hazard Layer (hazards.fema.gov ArcGIS REST): Flood Hazard Zones layer (parcel-polygon intersection for all four parcels), FIRM Panels layer (Panel 3720064700K, effective July 19, 2022), LOMR layer (0 records), accessed 2026-11-28.
  3. USFWS — National Wetlands Inventory, Wetlands layer (ArcGIS REST): parcel-polygon intersection for all four parcels (0 mapped polygons), accessed 2026-11-28.
  4. Town of Holly Springs — Town Council minutes, July 21, 2026 (CivicClerk official meeting file): public hearing on 25-REZ-05; 255-unit proposal; staff outline (priority level 3, Duncan Cook Road / Hazel Ridge tie-ins, EV outlets, façade standards, constructed wetlands, tree preservation along the southern stream).
  5. Town of Holly Springs — Planning Board minutes summary, August 25, 2026 (as published via NC GovWatch from the Town's records): consistency statement 5–1; recommendation 5–1; recorded objections; applicant's 47% open-space statement; eight-year buildout estimate.
  6. Town of Holly Springs — Town Council meeting record and minutes summary, October 20, 2026 (NC GovWatch; North Carolina Record transcript and summary): unanimous adoption of Ordinance RZ26-07, utility allocation and development agreement subject to changes; 365-day relocation commitment; $100,000 redirection; Town Attorney's further amendment; minutes approved on November 17, 2026 (Town Council consent agenda).
  7. Holly Springs Daily — Daventry approval coverage, October 2026 (reporting the Town's 746-page agenda packet, the staff report's "net gain of 175 dwelling units" framing, the owners' summary and letter filed with the application, and the packet's transportation commitments).
  8. Town of Holly Springs — Unified Development Ordinance (UDO), Supplement #7: §2.1.1 (district purposes), §2.2.1 Table 2.2.1-A (residential standards), §2.4 (Conditional Zoning Districts), Ch. 4 (open space & conservation), §7.2.1 Table 7.2-A (required improvements — public water/sewer), Ch. 11 (§11.5, §11.6, §§11.10–11.14), accessed 2026-11-27.
  9. Town of Holly Springs — Development Procedures Manual, Appendix A.02 (rezoning packet process), accessed 2026-11-27.
  10. Town of Holly Springs — Water Resource Management Policy, §§3.1–3.2 (DocumentCenter), accessed 2026-11-27.
  11. North Carolina General Statutes — Chapter 160D, Article 6, §§160D-601, 160D-602, 160D-604, 160D-605 (ncleg.gov, official text), accessed 2026-11-27.
  12. North Carolina General Statutes — §93A-83(f) (ncleg.gov) — basis for the no-valuation scope limit in §8.
  13. P&Z Radar (public historical archive of agenda packets) — case file 25-REZ-02 (Powell Place comparator in §5).

Not obtained, stated plainly: the full text of Ordinance RZ26-07 and its condition list; the executed development agreement (a further amendment was still to be proposed at the last record found); the full staff report for 25-REZ-05 (staff positions are cited here from the Town's published meeting records and packet reporting, not from the report itself); the project's traffic impact analysis; any post-approval major subdivision filing.


8. Scope & Disclaimer

This dossier compiles public records and published regulations; it is not a legal opinion. Retain NC land-use counsel to confirm.

Additional scope limits, stated plainly:

— End of sample dossier —

Evaluating a parcel in the Triangle?

A full PermitDossier pre-screen covers zoning, the entitlement pathway, flood, wetlands, utilities and case history for one parcel — compiled from public records, delivered as a dossier like this one. US$7,500 · 10 business days.